Report from Steve Schell, Cedar Hill's Project Manager:
During August, we will continue to work on sidewalks, underground storm drainage, install a retaining wall, excavation and fill. Pavement subgrade lime stabilization and concrete pavement should resume and continue into September and beyond.
The pavement construction will concentrate on the north side of the roadway between Belt Line Road to the new pavement on the west side of Baggett Branch Creek. Once this pavement is completed, we will switch the traffic to the new bridge construction on the other side of the roadway.
Around the same time, the traffic is switched to drive on the new bridge, we will be closing Lake Ridge Parkway at Mansfield road. Lake Ridge Parkway traffic to and from Mansfield Road will be diverted to Lakeview Drive. Two-way traffic will remain on Mansfield Road. Our best estimate at this time is for this closure to occur in the first half of September. Lake Ridge Parkway will likely be closed for six (6) weeks.
Please note, all construction schedules assume hundreds of smooth construction operations including cooperative weather. Needless to say, the construction schedules are subject to change.
As always, thank you for your cooperation and please feel free to contact the City if there are any concerns or questions regarding the construction.